WSP SW entrance -- will these fences really be coming down at last?
Completion date on sign: "Summer 2011" (Formerly Fall 2010)
The Lonely Chess Plaza
Washington Square Park Redesign: Phase IIB — the Chess Plaza and Southwestern Quadrant — under construction for 29 months (that’s 2 years and 5 months) is more than 17 months behind schedule (that’s one year and five months) from the original scheduled completion date and 9 months behind Phase IIA’s opening (June 2011) at which point it seemed likely it would be finished shortly thereafter.
It is now scheduled to be opened to the public at any moment – perhaps even tomorrow, Friday, March 2nd. At this point, we’ll believe it when we see it!
Depending on whom you ask, it was either the Parks Department’s stalling the project, a lack of any oversight by any governing body, or a problem between the contractor and the Parks Department which led to the monumental delay. Or some combination of all three.
This is what I wrote on June 2nd 2011 when Phase IIA – the eastern side of the Park – opened:
Phase II was scheduled for completion by Fall 2010; then we heard the end of the year (tho’ doubted it), then “Spring 2011,” then “by Memorial Day,” but park goers looked happy to be finally able to stream through the eastern end of the park.
Of course, this isn’t all of Phase II, since, for one, part of it (The Mounds and the Large Dog Run) was moved into Phase III. And Chess Plaza, technically still in Phase II, now Phase II-B, won’t be finished til the end of the month. At least, at last, it’s something!
WSP Blog chronicled the problems back in September 2010 outlining how the city’s parks department caused numerous delays in getting the job done, how the project was over-budget, and the fact that no governmental agencies were providing oversight.
Washington Square Park’s entire redesign – Phases I, II, and III – was budgeted and approved for $16 Million at the onset. Phase I alone — which moved the fountain to align with the Arch, reduced the public space around the fountain, and re-landscaped the NorthWest Quadrant, opened in May of 2009 — cost $13 Million.
Phase II was budgeted at $9 Million but will likely be $8 Million and that’s without the Large Dog Run and Mounds (included in the original figure).
Phase III (rest rooms and administrative building – the new “pergola”) had been budgeted at $9 Million (note – that’s before the cost of the Mounds and Dog Run are added in). Got all that?
Since the Parks Department’s projects continue to be seriously over-budget with no apparent oversight by any governing body, the project by the end will have more than doubled from its approved budget and is now projected for $30-$35 Million in cost.
A review of the finances:
Phase I cost: $13 Million (budgeted at $6 Million)
Phase II cost: $9.1 Million (budgeted at $9 Million but that figure was including the Dog Run and Mounds — both of which have been moved into Phase III)
Phase III: bid came in at “approximately 5.4 Million” according to the Parks Department
_______________________________________________________
Total projected thus far: $27.5 Million but there is no way Phase III will come in at $5.4 Million so we are at least $30 Million for a project which was approved at $16 Million at the onset.
It should be noted that Phase III contains the piece that the surrounding community and park users wanted completed first – the much neglected and deteriorating rest rooms. The Parks Department refused to accommodate this request; the city agency practically went out of its way to make sure this was completed last in the 3 phases of the project.
Work is presently scheduled to begin on Phase III — which now includes the Large Dog Run, the Mounds, Administrative Building, Rest Rooms and possibly perimeter sidewalks (much in need of repair!) — in April of this year.
At least, at last, the Chess Plaza will finally be opening! Will it be tomorrow? We’ll see…